1、Sondu/Miriu Hydropower ProjectSangoro Power PlantContract. No.SDM08EmployerKENGENEngineerNippon Koei Co.,Ltd.ContractorSinohydro Corporation Ltd.Document No.MD-06-B2-05-004 (R1)Page (s)5Date16th Mar 2011OPERATION AND MAINTENANCE MANUAL OF GENERATOR (Lot AP-2)R116th Mar 20111st SubmissionREV.DATEPREP

2、AREDCHECKEDENDORSEDAPPROVEDDescriptionFormat : A41 Operation of generator1.1 Preparations before start-up, including: a) Clean the work-yard and the generator set from any debris.b) Check the tightening condition, lock the gasket tightly, tack weld if necessary; keep the rotatable parts clean.c) Che

3、ck the inlet and outlet water pipelines, oil pipelines and valves, in order to know if there are leakages and problems of water flow in the pipe.d) Check the level of lubricating oil, oil number, oil quality, water pressure, and record the water temperature and ambient temperature.e) Check each conn

4、ecting cable, to make sure that the joints contact well and without rust, connection is right, and the marks are complete and distinct.f) Check if the equipments of high-pressure oil and the brake run normally, and if the brake pressure can meet the relevant requirements.g) Check the fire extinguish

5、ing system and other protecting facilities, to ensure security.h)Check the gaps between rotating parts and stationary parts, especially when there are dimension requirements.i) Make preparation work of recording before start-up.1.2 Initial no-load start-up operation The time of initial start-up of g

6、enerator, operating sequence and the general commander shall be determined through consultation among the buyer, the seller and the installation entity.1.2.1 Under the organization of the general commander, the operators and monitors shall get ready.1.2.2 Before start-up, first open the cooling wate

7、r of the upper and lower oil cooler and air cooler. The temperature of the oil in the oil tank shall not be lower than 100C, and that in the plastic bush tank shall not be lower than 50C.1.2.3 Push the rotor upward with high-pressure oil, and make the thrust pad lubricate to avoid dry friction.1.2.4

8、 Manually start the generator and let the rotating speed increase to 30% 50% of the nominal speed, so that the oil-bound film can be quickly formed. Let it run for a period of time and check the bearing temperature every 1 min., until the value keeps stable. There shall be no sharp increase of beari

9、ng temperature. At the same time, monitor the sound and observe every part to see if an abnormity occurs.1.2.5 When the generator running becomes stable and bearing temperature is normal, increase the rotating speed to the nominal speed gradually. Make the detecting records timely:a) bearing tempera

10、tureb) temperature of inlet cooling water and outlet cooling waterc) oil leveld)vibration of rack1.2.6 If the vibrationg of the generator meets the requirements (otherwise balance test will be needed), and the temperature of the bearing bush keeps stable, the machine can be stopped for check.1.2.7 C

11、hecking after the generator stops a) looseness, etc. in the parts of the rotor; b) resetting of the brake; c) Leakage of oil and water, and oil splashing of the upper and lower oil pipe.1.3 Initial on-load run1.3.1 Before the initial on-load run, the approval of relevant authority is needed, and the

12、 checking work of the phase sequence of network and the generator shall be well done. At the same time, open all the cooling water, and check water pressure and flow, level of lubricating oil, winding of stator and rotor, bearing, etc., and make good preparation before start-up.1.3.2 Increase exciti

13、ng current gradually at the nominal rotating speed. Only when generators voltage, frequency and phase angle meet the requirement of network, synchronize them and switch on, and then increase loads in phases, and at the same time make good records, like increase of temperature, vibration, etc.1.3.3 I

14、f there are no abnormalities, bring the load to rated power, maintain hour running, and check carefully the following items: a) temperature of stator and rotor winding; b) temperature of thrust bearing and guide bearing; c) temperature of inlet and outlet wind; d) vibration of the rack; e) electric

15、spark at the bus rings; f) Excitation data at the condition of no-load and on-load;1.3.4 Set the technical parameters according to relevant technical requirements.2 maintenance of generator2.1 The personnel of operation and maintenance of power station shall know and master the generators structure

16、and performance, and shall have a certain professional level on the operation and maintenance of generator, so as to guarantee the normal running of the generator. The operator shall record the service data on time, if the following phenomenon occur, shall stop it and check: a) vibrating and shaking

17、 abnormally; b) there is knocking sound; c) bearing temperature increasing suddenly, or oil level rising and lowering d) discontinuance of cooling water; e) temperature of the stator and the rotor rise too much; f) There are abnormal oil mist, smog, empyreuma, etc.2.2 Keep the inside of the generato

18、r clean and dry, without dust, oil, water, etc., so that can make the ventilation and elimination of heat of the motor easier, improve the insulation resistance, and prolong the operating life span of the motor. 2.3 Wash periodically the oil tanks of upper and lower rack and the copper pipe cooler,

19、and check if there is leakage, in order to guarantee safe operation.2.4 Take samples periodically and test the quality of lubricating oil.2.5 Check the pressure of collector rings, brush yokes and electric brush periodically and observe the wearing condition of carbon brush and electric spark.2.6 Ch

20、eck the braking system regularly for air pressure, oil pressure and wearing condition of braking-shoe.2.7Check all the connecting cables and joints periodically for looseness, poor contact, etc. causing overheating, rust, etc.2.8 The maintenance of stator includes:a) check insulation resistance of s

21、tator coil regularly;b) observe if there is heating at the ends of stator, looseness of the insulating parts, abnormal heating at the joints of stator, and deformation at the ends of winding;c) if there is looseness and abnormal noise of iron core of stator;d) if there is looseness at slot wedge, lo

22、ose weld between the pressed disc of stator and ventilation grid, etc.e) If there are looseness of the fastening parts in the base, or loose weld between the pressed disc of stator and ventilation grid, etc.2.9 The maintenance of rotor includes:a)check periodically if there is deformation of rotor,

23、especially after runaway;b) shall regularly check the insulation resistance of rotor winding to see if there is short-circuit.c) check the damping bar and damping ring to see if there is loose weld and deformation.d) check if there are looseness of all the fastening parts at the rotating parts.e) ob

24、serve if the iron core of magnetic pole is loose, and if the coil of magnetic pole movedf) check if the leading wire of rotor and leading wire between the poles of magnetic coil joint well and no loose.g) observe regularly the inside of the rotor support, and the space between the laminations of mag

25、netic yoke to avoid the entry of foreign matters.2.10 The maintenance of generator bearing includes:a) Generally, the temperature of tungsten bearing bush shall be less than 650C, and the maximum temperature can not exceed 700C. The temperature of hot oil in the plastic bearing bush can not exceed 5

26、00C, the temperature of the body of thrust bearing bush can not exceed 550C, during the running of generator, the value of resistance thermometer alarm and set stop value can be 10K15K and 15K20K higher than the normal running temperature respectively; and not to exceed the above mentioned value.b)

27、When start the generator in winter, the oil temperature in the oil tank can not be less than 100C. For the plastic bearing bush, start-up is allowed if the oil tank temperature is 50C and above.c) If not in use for over 48h, before start the generator, push the rotor upward to avoid dry friction and bush-burning. For plastic bush, the generator can be started directly without pushing the rotor within 30 days.d) To switch off, in case of tungsten bearing bush, only when the rotating speed slows down to 20%30% o

温馨提示

  • 1. 本站所有资源如无特殊说明,都需要本地电脑安装OFFICE2007和PDF阅读器。图纸软件为CAD,CAXA,PROE,UG,SolidWorks等.压缩文件请下载最新的WinRAR软件解压。
  • 2. 本站的文档不包含任何第三方提供的附件图纸等,如果需要附件,请联系上传者。文件的所有权益归上传用户所有。
  • 3. 本站RAR压缩包中若带图纸,网页内容里面会有图纸预览,若没有图纸预览就没有图纸。
  • 4. 未经权益所有人同意不得将文件中的内容挪作商业或盈利用途。
  • 5. 人人文库网仅提供信息存储空间,仅对用户上传内容的表现方式做保护处理,对用户上传分享的文档内容本身不做任何修改或编辑,并不能对任何下载内容负责。
  • 6. 下载文件中如有侵权或不适当内容,请与我们联系,我们立即纠正。
  • 7. 本站不保证下载资源的准确性、安全性和完整性, 同时也不承担用户因使用这些下载资源对自己和他人造成任何形式的伤害或损失。

评论

0/150

提交评论